A one-stop shop for overhead asset relocation
January 23, 2023

From surveying, design and drafting to project management and construction, Balpara’s range of specialisations cover all bases when it comes to overhead asset relocation. In this Q and A, Business Development Manager Neville Green explains the ins and outs of this specialised service, and why every construction project near existing power lines should consider an overhead asset assessment from the earliest stages of planning. 

 


In a nutshell, what is involved with overhead asset relocation? 


It relates to what they call the VESI (Victorian electricity supply industries) standard, which was developed by the five electricity distribution companies in Victoria. That standard describes minimum clearances from powerlines, both of new buildings being constructed and of things like cranes and scaffolds that might need to be put up in order to build those buildings. 


At Balpara we have an overhead survey division, who go out to where a new building is going to be constructed and conduct what’s called a sag and sway analysis. With certain weather conditions the lines move around, they sway back and forth, and we make sure under those circumstances the project meets the power industry standards for clearances.

 

If it doesn’t, design is required to move those powerlines away from that building. In some cases we place the cable underground, although this will depend on the cable. For example, at 22,000 volts, undergrounding the cable is more cost effective than if it’s a higher voltage. For 66,000 volts, it’s a fairly expensive exercise to underground the cable so we tend to put an offset arm on the existing poles to push it away from the building.  

 


Why is it important for clients to incorporate these kinds of works into their planning? 


Some companies may not have been exposed to the power industry authorities, and aren’t aware of the standards. So they start to do their planning and don’t realise until they get close to the construction phase that they’ve got an issue regarding existing power lines.  


It’s better to get onto this in the early stages because there’s a process involved in reviewing the site, obtaining all existing drawings out of the power companies, surveying and undertaking an analysis with all the information at hand. Then, once it is established that a powerline needs to be relocated, design work must be undertaken and approved by the power utility, along with costing approval by the client. This can take months, delaying the start of the build.  


Whereas if this work is undertaken during the building design phase, the designers have the option to allow for a bigger offset, or incorporate the cost and time of moving the powerlines into their overall budget and project plan. In any case it’s better than running into unexpected costs or delays down the track. The earlier this is addressed the better the outcome. 

 


Can you describe a specific example where Balpara has done this kind of work? 


One major example relates to a multi-million dollar development in Oakleigh in Melbourne’s eastern suburbs. It was a significant project, taking up virtually an entire block of Warrigal Road and Dandenong Road. On the Dandenong Road side there was a 22,000 volt line, so we undergrounded about 200m of cabling along that section of the road.  


Then along the Warrigal Road section there was a 66,000 volt line that needed to be moved in order to meet the clearance standards. We didn’t have to move the poles, we just pushed it out with an offset arm. There was an issue regarding the constructability of balconies that where in close proximity to the line and these required further clearances, which were accommodated.  


We’ve completed many similar projects but this was fairly major, making full use of Balpara’s range of services and expertise in this area. 

 



Why is Balpara well placed to provide this service? 


Balpara is a one-stop shop for this kind of project. We bring together our survey team, design team and drafting team, as well as project management and construction experts if we need to move the lines. We’re one of the only companies around that has a big overhead survey capacity – it's a specialised service, and a lot of companies can’t afford to have that service in-house. We have also serviced the power industry for over 20 years, and have strong relationships and a deep understanding of their standards, which enables us to streamline elements of the project. This area of expertise is unique and something we are proud of. 

 

Contact Balpara today to learn more about our asset relocation and other construction and project management services. 


You may also like

highway in melbourne
June 30, 2025
Balpara was contracted to carry out detailing and auditing services for the Lathams Road Upgrades in Carrum Downs, as part of Victoria’s Big Build. Project Overview This project involved multiple upgrades across a 2.5km section of Lathams Road. The upgrade included the addition of additional lanes going both ways, upgrading 13 intersections along the road, building a new bridge over the Peninsula Link, adding walking and cycling paths, widening existing roundabouts, and installing safety barriers. The project had a strong emphasis on community consideration and utilising sustainable project materials. As an example, drainage pipes and kerbs installed used recycled plastic and a social procurement strategy was formulated by the developer, Winslow, to actively engage Indigenous businesses, generating meaningful employment and promoting indigenous representation in the construction industry. These upgrades were completed with the intention of improving traffic flow and travel times, enhancing safety for pedestrians and cyclists and boosting the connectivity of local businesses in the Carrum Downs and Seaford community. Lathams Road is a vital road link for many of those in the surrounding community, and as such, these upgrades substantially improve traffic flow and access to surrounding industrial areas. Scope The team at Balpara was engaged to carry out detailing and auditing services for this road upgrade, including detailing, drafting and auditing. Detailing of the assets according to United Energy Standards: Public lighting poles Back of kerbs, both existing and new Conduits Finish surface levels Boundary lines Fences Other services in trench, i.e. storm water, comms, gas and more Drafting as-builts Auditing: Conduit installation to design Checking depths / offsets of conduits for compliance Maintaining compliant separation to other assets in the ground Checking backfills and warning tape compliance Checking cables sizes and type being installed Checking connections inside poles and pits Checking correct poles and lanterns, and pole numbers are being installed Producing audit reports for clients Value Add Balpara specialises in detailing and auditing and have a large team dedicated to all utilities across Victoria. With decades of experience in competitive bidding, Balpara delivers precise as-built drawings and audit reports, in accordance with United Energy and VESI Standards. Relevant Accreditation/Quality Standards Lighting along Lathams Road designed to AS/NZS 1158 – Category V3 requirements All assets installed in accordance with United Energy’s Standards and requirements VESI Standards VEDN Accredited Similar Projects Wells Road & Bardia Avenue Upgrades – Detailing & Auditing O’Shannasay Reservoir Melbourne Water Upgrade VEDN Civil, Electrical, Cable Hauling & Network Auditing Wyndham City Tarneit Road Public Lighting Project
June 16, 2025
Balpara was engaged by Civil & Road Contractor, Healey Infrastructure, to provide detailing and auditing services for the signalisation upgrade of Wells Road and Bardia Avenue in Frankston. Project Overview This upgrade was identified as necessary by Frankston City Council to: provide a safer and more accessible parking facility and road upgrades along Wells Rd and Bardia Avenue; to support active transport; reduce congestion; and improve overall safety for the growing Frankston City community. Road upgrades included the resurfacing of pavement, installation of new asphalt, upgrade of kerbing and drainage systems, re-painting line markings, and upgrading street lighting and traffic signal infrastructure. With construction completed in May 2025, the Frankston City community can now benefit from the enhanced traffic flow, improved lighting, safer roads and more accessible parking. Scope The team at Balpara provided detailing, drafting and auditing services for assets installed as part of the new road upgrades. Works included: Utilising GPS technology to accurately capture the locations of new underground assets to develop a comprehensive layout of asset locations. Producing precise as built plans in accordance with current UE standards. Auditing public lighting poles, conduit installations and electrical pit installations. An on-site electrical walkthrough on to prepare the pre-commissioning audit report for clients. Value Add Balpara holds accreditations with all Victorian Power Authorities and as such was able to accurately detail, draft and audit this project to UE and council standards, producing deliverables within the required timeframes and allowing for efficient and quality workmanship for the benefit of the Frankston City community. Relevant Accreditation/Quality Standards UE Standards VESI Standards VEDN Accredited  Similar Projects Major Roads Projects Victoria Kerang Solar Plant Oshannasay Reservoir Upgrade Ausnet Network Audits
a pump track
May 9, 2025
La Trobe City Council are planning to construct a Pump Track for residents to enjoy. This community space is designed to increase community connection in a positive environment.