Grand Central Estate NBN Construction and Electrical Design
November 16, 2021

Image copyright: https://www.stockland.com.au/residential/vic/grand-central/location


Balpara was engaged by Winslow Civil Construction to complete NBN construction for this large urban development project, alongside project management requirements. 


Project Overview

 

Balpara has previously provided a range of services for earlier stages of the Grand Central Estate development, including electrical and NBN design, public lighting design, project management, detailing and pre-Powercor auditing services. Balpara's services were again requested for stages 9 and 10 of the large multi-stage Tarneit development, seeing our team provide NBN construction, electrical design, drafting and project management services. 

 

Balpara was tasked with the electrical design on construction drawings for all lots while complying with technical standards, and producing detailing and as-built drawings in line with applicable standards. This plan showed the full extent of the main local duct, local network pits, local lateral duct and ‘starter pipe’ that were required, and formed the basis for telecommunications construction tenders. 

 

Our team was responsible for project managing the implementation of the electrical infrastructure, as well as coordinating the of tendering for electrical contractor in conjunction with the civil contractor. 


Project Scope

 

  • Creating the NBN Fibre Distribution Hub locations concept plan to ensure sufficient space was allocated and that all locations satisfied the NBN Co's comprehensive criteria list. 
  • Designing individual stage telecommunication ‘pit and pipe’ to NBN Co standards. 
  • Creating and submitting an application and plans for formal approval to the relevant authority. 
  • Constructing the pit and pipe network. 
  • Completing and submitting as-built plans for approval to NBN Co. 
  • Coordinating works between the civil and NBN installation contractors to ensure the works progressed in a timely manner that minimised risks. 
  • Requesting and overseeing the final compliance audit by NBN Co. 
  • Receiving audit results from NBN Co Approved Auditors and advising civil contractors of any rectification works required.


Value Add

 

Balpara was able to offer a range of services to the client, effectively fast-tracking the process. Our previous work on earlier stages of the project additionally gave our team greater knowledge of the site, allowing for faster identification of issues and their resolutions. 

 

Relevant Accreditation/Quality Standards

 

Balpara is ISO 9001 certified, all electrical project management and negotiations were performed by accredited PM2 mangers, and all electrical design was completed to Powercor Standards and NBN design to NBN Standards. 


Similar Projects

 

You may also like

highway in melbourne
June 30, 2025
Balpara was contracted to carry out detailing and auditing services for the Lathams Road Upgrades in Carrum Downs, as part of Victoria’s Big Build. Project Overview This project involved multiple upgrades across a 2.5km section of Lathams Road. The upgrade included the addition of additional lanes going both ways, upgrading 13 intersections along the road, building a new bridge over the Peninsula Link, adding walking and cycling paths, widening existing roundabouts, and installing safety barriers. The project had a strong emphasis on community consideration and utilising sustainable project materials. As an example, drainage pipes and kerbs installed used recycled plastic and a social procurement strategy was formulated by the developer, Winslow, to actively engage Indigenous businesses, generating meaningful employment and promoting indigenous representation in the construction industry. These upgrades were completed with the intention of improving traffic flow and travel times, enhancing safety for pedestrians and cyclists and boosting the connectivity of local businesses in the Carrum Downs and Seaford community. Lathams Road is a vital road link for many of those in the surrounding community, and as such, these upgrades substantially improve traffic flow and access to surrounding industrial areas. Scope The team at Balpara was engaged to carry out detailing and auditing services for this road upgrade, including detailing, drafting and auditing. Detailing of the assets according to United Energy Standards: Public lighting poles Back of kerbs, both existing and new Conduits Finish surface levels Boundary lines Fences Other services in trench, i.e. storm water, comms, gas and more Drafting as-builts Auditing: Conduit installation to design Checking depths / offsets of conduits for compliance Maintaining compliant separation to other assets in the ground Checking backfills and warning tape compliance Checking cables sizes and type being installed Checking connections inside poles and pits Checking correct poles and lanterns, and pole numbers are being installed Producing audit reports for clients Value Add Balpara specialises in detailing and auditing and have a large team dedicated to all utilities across Victoria. With decades of experience in competitive bidding, Balpara delivers precise as-built drawings and audit reports, in accordance with United Energy and VESI Standards. Relevant Accreditation/Quality Standards Lighting along Lathams Road designed to AS/NZS 1158 – Category V3 requirements All assets installed in accordance with United Energy’s Standards and requirements VESI Standards VEDN Accredited Similar Projects Wells Road & Bardia Avenue Upgrades – Detailing & Auditing O’Shannasay Reservoir Melbourne Water Upgrade VEDN Civil, Electrical, Cable Hauling & Network Auditing Wyndham City Tarneit Road Public Lighting Project
June 16, 2025
Balpara was engaged by Civil & Road Contractor to provide detailing and auditing services for the signalisation upgrade of Wells Road and Bardia Avenue in Frankston. Project Overview This upgrade was identified as necessary by Frankston City Council to provide a safer and more accessible parking facility and road upgrades along Wells Rd and Bardia Avenue, to support active transport, reduce congestion, and improve overall safety for the growing Frankston City community. Road upgrades included the resurfacing of pavement, installation of new asphalt, upgrade of kerbing and drainage systems, re-painting line markings, and upgrading street lighting and traffic signal infrastructure. ๏ปฟ With construction completed in May 2025, the Frankston City community can now benefit from the enhanced traffic flow, improved lighting, safer roads and more accessible parking. Scope The team at Balpara provided detailing, drafting and auditing services for assets installed as part of the new road upgrades. Works included: Utilising GPS technology to accurately capture the locations of new underground assets to develop a comprehensive layout of asset locations. Producing precise as built plans in accordance with current UE standards. Auditing public lighting poles, conduit installations and electrical pit installations. An on-site electrical walkthrough on to prepare the pre-commissioning audit report for clients. Value Add Balpara holds accreditations with all Victorian Power Authorities and as such was able to accurately detail, draft and audit this project to UE and council standards, producing deliverables within the required timeframes and allowing for efficient and quality workmanship for the benefit of the Frankston City community. Relevant Accreditation/Quality Standards UE Standards VESI Standards VEDN Accredited Similar Projects Major Roads Projects Victoria Kerang Solar Plant Oshannasay Reservoir Upgrade Ausnet Network Audits
a pump track
May 9, 2025
La Trobe City Council are planning to construct a Pump Track for residents to enjoy. This community space is designed to increase community connection in a positive environment.