Balpara has been engaged to perform various asset set-out survey tasks for Melbourne’s North East Link Freeway Project to ensure correct construction of underground and overhead utility assets.


Project Overview


The North East Link project creates a new 11 km connection between the M80 Metropolitan Ring Road at Greensborough and the M3 Eastern Freeway at Doncaster. The project aims to reduce travel time by 35 minutes, take up to 15,000 trucks off local roads and see the creation of new walkways, bike paths and Melbourne’s first dedicated bushway.


Balpara is helping to bring the 3D designs of CPB and Cardno to life, undertaking a set-out survey for future trenches to ensure the safe and effective construction of HV powerlines. Due to the presence of high-pressure gas mains along Greensborough Road, Balpara provided these surveying services with the utmost care and precision to ensure safe construction.


Once trenches are dug, Balpara will also survey each trench, ensuring they are accurate to the 3D designs; correct in depth and alignment.


Project Scope

 

  • Providing project management by liaising with CPB and Cardno to ensure 3D survey data compatibility
  • Provision of underground asset locating and assessment services
  • Preparing road markings accurate with 3D designs to guide the location and dimensions of trenches to ensure accuracy
  • Using advanced technology including Robotic Total Stations and GPS field systems to ensure accuracy to within ±20mm
  • Surveying of trenches to ensure correct depth and alignment of HV powerlines in accordance with 3D designs
  • Completing all works during night shift as required
  • Providing all services in line with our VEDN accreditation


Value Add

 

Balpara is VEDN accredited, and this project was undertaken adhering to all VESI training requirements and best practise surveying techniques.


Relevant Accreditation/Quality Standards

 

  • Balpara has completed all training aligned to the VESI requirements that allows us to work to CitiPower standards.


Similar Projects

 


Download the North East Link case study here.

You may also like

March 28, 2025
Balpara was engaged by civil constructor, Directbor, to provide detailing and drafting services to connect the Kerang Solar Plant to the nearby Kerang Terminal Station. Project Overview The Kerang Solar Plant in Victoria is a BSR Energy project, which aims to generate enough clean and reliable energy to offset the annual consumption of approximately 16,000 homes, contributing to a more sustainable future while reducing reliance on traditional power sources. Construction commenced in March 2024, and is projected to save 66,380 tonnes of CO2-equivalent emissions annually. The land parcel is over 64 hectares in size, with the plan to visually integrate into the surrounding agricultural landscape with extensive planting of native flora around the entire project perimeter. The bell-mouth intersection off Lodden Valley Highway will be upgraded for improved accessibility and safety as part of this project. Scope Balpara’s involvement in the project was undertaken over the course of a month starting in August 2024, with Directbor engaging the team on behalf of Powercor. The Balpara team completed detailing and drafting of assets connecting the new Kerang Solar Plant to Powercor’s distribution network. Balpara employed GPS technology to accurately capture underground asset locations and create a comprehensive plan of assets within the short timeframe required. The project scope included: Capturing new underground asset locations to required standard using GPS equipment. Creating as-built plans of relevant assets to current Powercor standards. Providing captured 3D data to Powercor for future asset relocations. Value Add Balpara provided timely and accurate drawings and was able to quickly meet the needs of client variations. The Balpara team is well versed in working with all utility standards, including Powercor, which helped to streamline the project. Accreditations Powercor Standards
technician looking at a substation
March 19, 2025
Balpara was engaged by Powercor to conduct a turnkey solution at the Echuca Zone Substation. This included Project Management of Feature Surveying, Geotechnical Services and Contaminated Soil Testing.
Glen Waverley Substation
February 24, 2025
Balpara was engaged by United Energy to carry out feature surveying, incorporating ground penetrating radar surveys for the Glen Waverley Zone Substation.
Share by: