Balpara was engaged by Commercial & Industrial Property (CIP) to provide electrical designs for the relocation of 66kV and 22kV overhead powerlines running along a major road to create a double 66kV and 22kV structure on the Drystone Industrial Estate along Leakes Road, Truganina.

Scope

We were engaged by CIP to perform the project management and all the double 66/22kV powerline surveying and design associated with this project.

This included:

 

Balpara’s Delivery

 

To date, Balpara has designed two stages to the satisfaction of CIP, with a third in progress and a fourth to commence soon.

The first stage of the project has been constructed within the assigned time frames and to budget, the second is in progress with other stages to follow.

 

ISO9001 | Our Commitment to Quality

Balpara has held ISO9001 certification for more than six years now without any non-conformances and we are currently transitioning from ISO9001:2008 to 2015. This being a reflection of our commitment to continuous improvement and quality.

Our Technical Expertise

We provide project management, electrical engineering, surveying, VEDN auditing, drafting, 3D modelling & scanning and detailing as well as structural engineering services. Our services can be delivered on location or from the Balpara office.

You may also like

March 28, 2025
Balpara was engaged by civil constructor, Directbor, to provide detailing and drafting services to connect the Kerang Solar Plant to the nearby Kerang Terminal Station. Project Overview The Kerang Solar Plant in Victoria is a BSR Energy project, which aims to generate enough clean and reliable energy to offset the annual consumption of approximately 16,000 homes, contributing to a more sustainable future while reducing reliance on traditional power sources. Construction commenced in March 2024, and is projected to save 66,380 tonnes of CO2-equivalent emissions annually. The land parcel is over 64 hectares in size, with the plan to visually integrate into the surrounding agricultural landscape with extensive planting of native flora around the entire project perimeter. The bell-mouth intersection off Lodden Valley Highway will be upgraded for improved accessibility and safety as part of this project. Scope Balpara’s involvement in the project was undertaken over the course of a month starting in August 2024, with Directbor engaging the team on behalf of Powercor. The Balpara team completed detailing and drafting of assets connecting the new Kerang Solar Plant to Powercor’s distribution network. Balpara employed GPS technology to accurately capture underground asset locations and create a comprehensive plan of assets within the short timeframe required. The project scope included: Capturing new underground asset locations to required standard using GPS equipment. Creating as-built plans of relevant assets to current Powercor standards. Providing captured 3D data to Powercor for future asset relocations. Value Add Balpara provided timely and accurate drawings and was able to quickly meet the needs of client variations. The Balpara team is well versed in working with all utility standards, including Powercor, which helped to streamline the project. Accreditations Powercor Standards
technician looking at a substation
March 19, 2025
Balpara was engaged by Powercor to conduct a turnkey solution at the Echuca Zone Substation. This included Project Management of Feature Surveying, Geotechnical Services and Contaminated Soil Testing.
Glen Waverley Substation
February 24, 2025
Balpara was engaged by United Energy to carry out feature surveying, incorporating ground penetrating radar surveys for the Glen Waverley Zone Substation.