Bushfire Mitigation Powerline Replacement Program
March 21, 2020

Over the last six years, Balpara’s surveying team has been extensively involved in this major government fire prevention initiative, seeing us work alongside Powercor across Western Victoria. Our experience in electrical engineering, asset location and assessment, detailing, drafting and electrical project management has seen our team sought out for the duration of this ongoing project.

 

Project Overview

 

Balpara has provided continued assistance in this ongoing program that involves removing hundreds of kilometres of dangerous or old overhead powerlines in ‘high risk’ bushfire areas. These are then replaced with high voltage underground electrical cables, installed using advanced drilling equipment with almost zero environmental impact or disturbance. These electrical cables are required to service entire regional suburbs in each project area. To date, Balpara has been involved in over 300km of underground electrical cable installation and is set to be involved in another large section throughout 2020.

 

Project Scope

 

  • Feature surveying of electrical cables and associated roads, fences and boundaries in sections of every 3 – 10 metres for up to 50km per regional suburb.
  • Production of As-Built drawings using processed survey results for every 3 – 10 metre section correct to MGA coordinates.
  • Approximately 500 As-Built drawings delivered per regional suburb, providing accurate asset locations for future maintenance and safety.
  • Produce works to within ±20mm accuracy to MGA coordinates ensuring information can be used by ‘dial before you dig’ to prevent high voltage cables being struck by future civil works.


Value Add

 

The longevity of Balpara’s contract demonstrates our proven ability to continually meet and exceed expectations with high-quality and thorough work.

 

Relevant Accreditation/Quality Standards

 

  • This project is undertaken adhering to all VESI training requirements, best practice surveying techniques and Powercor’s comprehensive site and office-based drafting standards.


You may also like

March 28, 2025
Balpara was engaged by civil constructor, Directbor, to provide detailing and drafting services to connect the Kerang Solar Plant to the nearby Kerang Terminal Station. Project Overview The Kerang Solar Plant in Victoria is a BSR Energy project, which aims to generate enough clean and reliable energy to offset the annual consumption of approximately 16,000 homes, contributing to a more sustainable future while reducing reliance on traditional power sources. Construction commenced in March 2024, and is projected to save 66,380 tonnes of CO2-equivalent emissions annually. The land parcel is over 64 hectares in size, with the plan to visually integrate into the surrounding agricultural landscape with extensive planting of native flora around the entire project perimeter. The bell-mouth intersection off Lodden Valley Highway will be upgraded for improved accessibility and safety as part of this project. Scope Balpara’s involvement in the project was undertaken over the course of a month starting in August 2024, with Directbor engaging the team on behalf of Powercor. The Balpara team completed detailing and drafting of assets connecting the new Kerang Solar Plant to Powercor’s distribution network. Balpara employed GPS technology to accurately capture underground asset locations and create a comprehensive plan of assets within the short timeframe required. The project scope included: Capturing new underground asset locations to required standard using GPS equipment. Creating as-built plans of relevant assets to current Powercor standards. Providing captured 3D data to Powercor for future asset relocations. Value Add Balpara provided timely and accurate drawings and was able to quickly meet the needs of client variations. The Balpara team is well versed in working with all utility standards, including Powercor, which helped to streamline the project. Accreditations Powercor Standards
technician looking at a substation
March 19, 2025
Balpara was engaged by Powercor to conduct a turnkey solution at the Echuca Zone Substation. This included Project Management of Feature Surveying, Geotechnical Services and Contaminated Soil Testing.
Glen Waverley Substation
February 24, 2025
Balpara was engaged by United Energy to carry out feature surveying, incorporating ground penetrating radar surveys for the Glen Waverley Zone Substation.
Share by: