Fisherman’s Bend power cable upgrade works
June 21, 2023

Balpara was engaged by a utilities client to provide surveying, detailing and as-built drafting for 66kV power upgrade at Fisherman’s Bend in Port Melbourne. This included Balpara’s 3D scanning and modelling service.


Project Overview


This project involved the excavation of a 2.5km long trench for the installation of new 66kv underground power circuits at Fisherman’s Bend. This entailed displacing a very large volume of soil as well as the construction of a number of pits required to accommodate the joints between lengths of cable. Through our 3D scanning and modelling service Balpara was able to provide the utilities client with a very accurate calculation of the volume of displaced soil, as well as detailed records of the location and makeup of the underground assets, including the joints.


Project Scope


  • Providing electrical distribution surveying, detailing and as-built drafting 
  • 3D modelling of trenches and electrical assets for production of 3D volume calculations 
  • 3D mapping of 66kV cable joints 

 

Value Add

 

Balpara is one of the first companies to offer a 3D scanning and modelling service to the electrical distribution industry. The service provided the client with a high level of accuracy regarding the volume of displaced soil and the location of underground assets.

 

Relevant Accreditation/Quality Standards


  • VESI accreditation 
  • Project-specific induction


Similar Projects

 

  • North-East Link 
  • Craigieburn Rd Upgrade Project

You may also like

March 28, 2025
Balpara was engaged by civil constructor, Directbor, to provide detailing and drafting services to connect the Kerang Solar Plant to the nearby Kerang Terminal Station. Project Overview The Kerang Solar Plant in Victoria is a BSR Energy project, which aims to generate enough clean and reliable energy to offset the annual consumption of approximately 16,000 homes, contributing to a more sustainable future while reducing reliance on traditional power sources. Construction commenced in March 2024, and is projected to save 66,380 tonnes of CO2-equivalent emissions annually. The land parcel is over 64 hectares in size, with the plan to visually integrate into the surrounding agricultural landscape with extensive planting of native flora around the entire project perimeter. The bell-mouth intersection off Lodden Valley Highway will be upgraded for improved accessibility and safety as part of this project. Scope Balpara’s involvement in the project was undertaken over the course of a month starting in August 2024, with Directbor engaging the team on behalf of Powercor. The Balpara team completed detailing and drafting of assets connecting the new Kerang Solar Plant to Powercor’s distribution network. Balpara employed GPS technology to accurately capture underground asset locations and create a comprehensive plan of assets within the short timeframe required. The project scope included: Capturing new underground asset locations to required standard using GPS equipment. Creating as-built plans of relevant assets to current Powercor standards. Providing captured 3D data to Powercor for future asset relocations. Value Add Balpara provided timely and accurate drawings and was able to quickly meet the needs of client variations. The Balpara team is well versed in working with all utility standards, including Powercor, which helped to streamline the project. Accreditations Powercor Standards
technician looking at a substation
March 19, 2025
Balpara was engaged by Powercor to conduct a turnkey solution at the Echuca Zone Substation. This included Project Management of Feature Surveying, Geotechnical Services and Contaminated Soil Testing.
Glen Waverley Substation
February 24, 2025
Balpara was engaged by United Energy to carry out feature surveying, incorporating ground penetrating radar surveys for the Glen Waverley Zone Substation.
Share by: