Blog Layout

Richmond Terminal Substation (RTS) Project
December 19, 2017



Located in Mary Street, Richmond, the RTS is an integral part of Victoria’s electricity infrastructure. It is one of several high voltage electricity terminal stations that serve inner Melbourne. It receives HV electricity via transmission lines which it converts to LV.

Electricity terminal stations have a finite lifespan, requiring upgrades after appr. 50 years. As the RTS was built in the 60s, it needed to be rebuilt and modernised. The upgrade involved replacement of most of the electrical equipment on site and construction of new buildings to house some of the equipment. The RTS is owned by AusNet services and feeds both the CitiPower and United Energy networks.

Balpara’s Initial Involvement

Balpara was engaged to GPS detail and draft 66kV related assets on the Richmond Terminal Substation (RTS).

There was substantial detailing required around the terminal substation divided up into multiple stages.

To ensure accurate measurements were taken under challenging circumstances, we used GPS equipment to detail the works. The initial stage contained around a month’s civil work with over a dozen site visits with additional work stages to follow.

Added Value to the Project

In addition to works completed, we are currently working on a millimetre accurate 3D construction set-out model of all the new 66kV concrete poles inside and locally outside the RTS.

This is being done in collaboration with the CitiPower engineering design team. The newly created 3D model will be used to also produce new 2D Construction Standard Drawings for the CitiPower Standards Group.

These drawings will form part of CitiPower’s Construction Standards for major 66kV Pole works into the future.

You may also like

March 28, 2025
Balpara was engaged by civil constructor, Directbor, to provide detailing and drafting services to connect the Kerang Solar Plant to the nearby Kerang Terminal Station. Project Overview The Kerang Solar Plant in Victoria is a BSR Energy project, which aims to generate enough clean and reliable energy to offset the annual consumption of approximately 16,000 homes, contributing to a more sustainable future while reducing reliance on traditional power sources. Construction commenced in March 2024, and is projected to save 66,380 tonnes of CO2-equivalent emissions annually. The land parcel is over 64 hectares in size, with the plan to visually integrate into the surrounding agricultural landscape with extensive planting of native flora around the entire project perimeter. The bell-mouth intersection off Lodden Valley Highway will be upgraded for improved accessibility and safety as part of this project. Scope Balpara’s involvement in the project was undertaken over the course of a month starting in August 2024, with Directbor engaging the team on behalf of Powercor. The Balpara team completed detailing and drafting of assets connecting the new Kerang Solar Plant to Powercor’s distribution network. Balpara employed GPS technology to accurately capture underground asset locations and create a comprehensive plan of assets within the short timeframe required. The project scope included: Capturing new underground asset locations to required standard using GPS equipment. Creating as-built plans of relevant assets to current Powercor standards. Providing captured 3D data to Powercor for future asset relocations. Value Add Balpara provided timely and accurate drawings and was able to quickly meet the needs of client variations. The Balpara team is well versed in working with all utility standards, including Powercor, which helped to streamline the project. Accreditations Powercor Standards
technician looking at a substation
March 19, 2025
Balpara was engaged by Powercor to conduct a turnkey solution at the Echuca Zone Substation. This included Project Management of Feature Surveying, Geotechnical Services and Contaminated Soil Testing.
Glen Waverley Substation
February 24, 2025
Balpara was engaged by United Energy to carry out feature surveying, incorporating ground penetrating radar surveys for the Glen Waverley Zone Substation.
Share by: